Page 66 - การดาดผิว
P. 66
5 - 9
ตารางท 5-3 (ตอ)
่
ี
่
MAX. DESIGN TIRE CONTACT DISIGN CURVE FIGURE RECOMMENDED MINIMUM THICKNESS OF PAVEMENT AND BASE (In.)
AIRCRAFT TAKE OFF LOAD PRESS AREA TO BE USED 80 CBR BASE 100 CBR BASE
WT. Kips WT. Kips P.S.I. SQ.In. EMERG. MIN. FULL PAVEMENT BASE PAVEMENT BASE
BOMBER EMERG. MIN. FULL EMERG. MIN. FULL EMERG. MIN. FULL EMERG. MIN. FULL
F-104F 27.9 12.8 272 47 5-7 5-8 5-9 2 2 2 6 6 6 2 2 2 6 6 6
F-105F 54.6 23.4 220 106 5-7 5-8 5-9 2 2.5 3 6 6 6 2 2 2 6 6 6
F-106B 39.6 18.1 285 63.0 5-7 5-8 5-9 2 2.5 2.5 6 6 6 2 2 2.5 6 6 6
F-111A 80 36.8 150 244 - - - 2 - - - - - - - - - - -
F-4C 59.1 26 255 102 5-7 5-8 5-9 2.5 3 3.5 6 6 6 2 2.5 3 6 6 6
F-5A 19.9 8.6 210 41 5-7 5-8 5-9 2 2 2 6 6 6 2 2 2 6 6 6